UETN Projects and Initiatives For FY2016
This initiatives list represents projects that will be addressed during fiscal year 2016 (Q1: July - Sept, Q2: Oct - Dec, Q3: Jan - March, Q4: April - June). This does not include ongoing operations or maintenance items.
Network Services Application Services Support Services Operations
Network Services

1
Implement Ethernet 10 Gb backbone circuit to Hurricane High School (Washington District)

Lead: Technical Services

Last Update: 10/14/15
2
Engineer and implement Washington School District increased capacity circuits

Lead: Technical Services

Last Update: 7/14/16
 3
Redesign and bid all Alpine Elementary Schools

Lead: Technical Services

Last Update: 10/14/15
 4
Engineer and implement 10GB backbone from UVU Orem to USU San Juan – Blanding

Lead: Technical Services

Last Update: 10/14/15
 5
Install CIB funded licensed microwave radios to Montezuma Creek, Monument Valley, and Navajo Mountain

Lead: Technical Services

Last Update: 10/14/15
 6
Design, procure, and install 48 RUS Grant funded collaborative video classrooms and associated infrastructure.

Lead: Technical Services

Last Update: 7/14/16
 7
Design, procure, and install eight STEM collaborative video classrooms.

Lead: Technical Services

Last Update: 7/14/16
 8
Engineering, coordinate with regional stakeholders and relocated all services within the San Juan Media Center to new data center.

Lead: Technical Services

Last Update: 8/8/16

 

 9
Install 10 gigabit Ethernet backbone circuit between UVU-Orem and UVU-Wasatch (Heber, UT)

Lead: Technical Services

Last Update: 10/14/15
 10
Install new 10 gigabit Ethernet backbone circuit to Nebo School District

Lead: Technical Services

Last Update: 10/14/15
 11
Install new 10 gigabit Ethernet backbone circuit to Provo School District

Lead: Technical Services

Last Update: 10/14/15
 12
Replace/Refresh all Cisco 3750G switches

Lead: Technical Services

Last Update: 7/14/16
 13
Continue IVC/Collaborative Video refresh project

Lead: Technical Services
Deferred
80%

Last Update: 8/8/16
 14
Coordinate Four Corners Network Development Project

Lead: Technical Services
Deferred
60%

Last Update: 8/8/16
 15
Continue to identify and evaluate emerging synchronous video solutions based on the identified needs of the UETN stakeholder.

Lead: Technical Services
Ongoing

Last Update: 8/8/16
 16
Continue IT Asset Management Project

Lead: Technical Services
Ongoing

Last Update: 10/14/15
 17
Continue Technical Services equipment replacement/refresh.

Lead: Technical Services
Ongoing

Last Update: 8/8/16
 18
Coordinate CIB funded structural improvements to Cold Springs Communication site (Abajo Mountains outside of Monticello)

Lead: Technical Services
Deferred
20%

Last Update: 8/8/16
 19
Coordinate CIB funded tower replacement at Cedar Mesa (Just above Moki Dugway overlooking Bluff and Mexican Hat, UT)

Lead: Technical Services
Deferred
80%

Last Update: 8/8/16
 20
Coordinate installation of CIB funded fiber based broadband to USU-Monticello.

Lead: Technical Services

Last Update: 10/14/15
 21
Coordinate, engineer and install USHE alternate 10 gigabit broadband circuit from USHE Offices at Gateway to the Downtown Data Center.

Lead: Technical Services

Last Update: 8/8/16
 22
Engineer and implement new UVU "BONFIRE" DWDM ROADM leg.

Lead: Technical Services

Last Update: 8/8/16
 23
Engineer and implement new UU Hospital – Farmington leg "BONFIRE" DWDM ROADM leg.

Lead: Technical Services

Last Update: 9/10/15
 24
Define, communicate and implement new UEN PoP requirements.

Lead: Technical Services
Deferred
90%

Last Update: 8/8/16
 25
Award and coordinate network engineering study associated with SB222.

Lead: Technical Services

Last Update: 8/8/16
 26
Award and coordinate statewide inventory associated with SB222.

Lead: Technical Services

Last Update: 8/8/16
 27
Statewide annual broadband RFP.

Lead: Technical Services
80%

Last Update: 10/14/15
 28
Develop Risk Assessment methodology

Lead: Technical Services

Last Update: 8/8/16
 29
Conduct Security Penetration Test of UEN (PEN)

Lead: Technical Services

Last Update: 8/8/16
 30
Redesign UTN network

Lead: P.Bonsavage
90%

Last Update: 9/15/15
 31
Upgrade UTN network core

Lead: P.Bonsavage
35%

Last Update: 9/15/15
 32
Conduct HCF RFP#1 to upgrade network capacity and add sites

Lead: D.LaMarche & P.Bonsavage
0%

Last Update: 9/15/15
 33
Implement secondary core location and host site (St George)

Lead: P.Bonsavage
0%

Last Update: 9/15/15
 34
Conduct HCF RFP#2 to upgrade network capacity and add sites

Lead: D.LaMarche & P.Bonsavage
0%

Last Update: 9/15/15
 35
Relocate primary network core from EBC to DDC

Lead: P.Bonsavage
0%

Last Update: 9/15/15
 36
Build UTN Server Test Lab

Lead: R.Evans
10%

Last Update: 9/15/15
 37
Complete and utilize IHC network connection into UTN

Lead: M.Cesarini

Last Update: 5/3/16
 38
Migrate UTN Resources to shared UEN/UTN Infrastructure

Lead: P.Bonsavage
65%

Last Update: 9/15/15
 39
Assess connectivity and telehealth capacity for specified Utah Indian tribes

Lead: D.LaMarche
0%

Last Update: 9/15/15
 40
Plan to implement measures to meet PCI DSS 3.0 compliance.

Lead: P.Bonsavage
0%

Last Update: 9/22/15
Application Services

 1
Develop video and educational materials for SciTech Now grant.

Leads: K.Garrett & K.Krier

Last Update: 3/1/16
 2
Upgrade Equella to version 6.4 with user interface enhancements.

Lead: K.Garrett

Last Update: 11/24/15
 3
Develop new workflow to accommodate new broadcast infrastructure.

Leads: K.Garrett
Deferred

Last Update: 5/3/16
 4
Implement automated closed captioning service. Help train and assist in implementation with UTTC.

Leads: K.Garrett

Last Update: 1/5/16
 5
Create training and promotional materials to support new teacher-upload feature of eMedia.

Leads: K.Garrett
Deferred

Last Update: 5/3/16
 6
Support the Utah Women and Leadership Project (UWLP) and Utah Women and Education Initiative (UWEI) project with digital and broadcast media.

Leads: K.Garrett

Last Update: 4/18/16
 7
Produce eight arts and science/technology segments for UEN-TV programs "Art Connection" and "SciTech Now".

Leads: K.Garrett
Ongoing

Last Update: 5/3/16
 8
Establish production standards and guidelines for digital and broadcast media.

Leads: K.Garrett
Deferred

Last Update: 5/3/16
 9
Refresh interstitials and promotional content on UEN-TV.

Leads: K.Garrett
25%
Deferred

Last Update: 7/14/16
 10
Expand partnership with Utah's Hogle Zoo to produce short videos to support Utah's core science standards.

Leads: K.Garrett

Last Update: 5/3/16
 11
Implement new LTI to connect eMedia resources in Canvas.

Leads: K.Garrett

Last Update: 10/14/15
 12
Develop an Online IVC Site Planning Form

Lead: R.Keele

Last Update: 8/13/15
 13
Develop ResearchQuests.org web site for the Natural History Museum of Utah

Lead: M.Dumas

Last Update: 3/31/16
 14
Support UtahFutures

Lead: L.Hunter
K.Krier

Last Update: 5/3/16
 15
Finish making the various websites UEN hosts and maintains responsive

Lead: M.Dumas

Last Update: 5/5/16
 16
Develop Security Web Portal

Lead: R.Keele & UEN Security Dept.
40%
Deferred

Last Update: 8/1/16
 17
Develop an interface that will automatically process UTN's Jabber request form

Lead: R.Keele

Last Update: 9/2/15
 18
Develop Apps for Acano integration

Lead: R.Keele
Deferred

Last Update: 8/1/16
 19
Develop a UTN scheduling form

Lead: R.Keele

Last Update: 10/2/15
 20
Integrate the new Professional Development administrative / registration system with UEN.org

Lead: R.Keele & J.Brooksby
Eliminated

Last Update: 8/1/16
 21
Enhance student interactives to make them searchable

Lead: R.Keele
75%
Deferred

Last Update: 8/1/16
 22
Transfer Utah Middle School Math website to UEN's web server

Lead: K.Krier & M.Dumas

Last Update: 7/16/15
 23
Complete iUTAH Redesign

Lead: J.Anderson

Last Update: 11/24/15
 24
Update the Finance In The Classroom website

Lead: M.Dumas

Last Update: 5/5/16
 25

Lead: M.Dumas
80%
Deferred

Last Update: 8/1/16
 26
Implement a promotional plan for UEN's Online Tools

Lead: K.Krier & K.Garrett

Last Update: 1/8/16
 27
Implement new videoconferencing platform for telehealth

Lead: M.Cesarini
10%

Last Update: 9/15/15
 28
Install and deploy new Acano videoconferencing bridge

Lead: M.Cesarini
50%

Last Update: 9/15/15
 29
Deploy telehealth equipment in selected health care facilities

Lead: P.Carroll & M.Cesarini
35%

Last Update: 9/15/15
 30
Implement Vulnerability Compliance procedure

Lead: S.Black & J.Desha

Last Update: 1/8/16
 31
Implement UTN WebEx application

Lead: M.Cesarini
10%

Last Update: 9/15/15
 32
Develop Media Services staff training document

Lead: R. Evans
51%

Last Update: 9/15/15
 33
Develop inventory lifespan tracking module in UTED

Lead: R.Evans
15%

Last Update: 9/15/15
 34
Pilot telehealth services to schools

Lead: P.Carroll
0%

Last Update: 9/15/15
 35
Add value-added services for UTN member sites

Lead: S.Black & P.Bonsavage
10%

Last Update: 9/15/15
 36
Evaluate new paging system

Lead: M.Cesarini
10%

Last Update: 9/15/15
 37
Implement JIRA for trouble tickets

Lead: S.Black
40%

Last Update: 9/15/15
 38
Evaluate JIRA as a tool for project management/time tracking

Lead: R.Evans & M.Cesarini
0%

Last Update: 9/15/15
 39
Automate Jabber account creation process

Lead: R.Evans
95%

Last Update: 9/15/15
 40
Explore options for Mobile Device Management and Secure Text Messaging for UTN member sites

Lead: M.Cesarini
0%

Last Update: 9/15/15
 41
Develop processes including support and training required to roll-out Cisco Collaborative Meeting Room (CMR) with WebEx to UEN stakeholders.

Lead: Technical Services

Last Update: 8/8/16
 42
Complete Database Migration to (MS SQL and PostgreSQL)

Lead: B.Peterson

Last Update: 9/26/15
 43
Move to Downtown Data Center (DDC)

Lead: B.Peterson
95%

Last Update: 7/1/15
 44
Virtualize Web and Database server environments.

Lead: B.Peterson

Last Update: 1/4/16
 45
Retool Web Hosting Toward Automation

Lead: B.Peterson
Ongoing

Last Update: 7/1/15
 46
Deploy DNS IPv6 anycast addresses for native IPv6 name resolution throughout the network.

Lead: B.Peterson
30%

Last Update: 7/1/15
 47
Implement UDA Project Go

Lead: B.Peterson
0%

Last Update: 7/1/15
 48
Update the lesson plan tool

Lead: K.Branson
Deferred
90%

Last Update: 8/12/16
 49
Conduct Identity management pilot (InCommon / Shibboleth)

Leads: K.Branson & J.Stewart
Deferred
55%

Last Update: 8/12/16
 50
Complete UEN Web-Service Framework

Lead: K.Branson

Last Update: 8/12/16
 51
Upgrade my.uen portal

Lead: K.Branson
Deferred
5%

Last Update: 4/19/16
 52
Move off Sybase ASE

Lead: K.Branson

Last Update: 9/30/15
 53
Rewrite all Perl/CGI applications

Lead: K.Branson
Deferred
95%

Last Update: 8/12/16
 54
Migrate applications to Java 7, Tomcat 7, Ubuntu VMs, and PostresSQL

Lead: K.Branson

Last Update: 4/19/16
 55
Better build management with Maven and SVN

Lead: K.Branson
Deferred
80%

Last Update: 4/19/16
 56
Product maintenance and functional enhancements

Lead: K.Branson
Ongoing

Last Update: 4/19/16
 57
Develop new Districts tool

Lead: K.Branson

Last Update: 4/19/16
 58
Update Rubric Tool

Lead: K.Branson
Deferred
90%

Last Update: 8/12/16
 59
Framework security upgrades

Lead: K.Branson
Deferred
80%

Last Update: 8/12/16
 60
Develop Unit Tool

Lead: K.Branson
Deferred
0%

Last Update: 9/30/15
 61
Rewrite BIRT Reports

Lead: K.Branson
Eliminated

Last Update: 4/13/16
 62
Externalize application configurations

Lead: K.Branson
Deferred
60%

Last Update: 4/19/16
 63
JIRA custom plugins for QuickTicket functionality

Lead: K.Branson
Deferred
10%

Last Update: 4/19/16
 64
Develop an Online Monitoring and Observation Matrix form and reports

Lead: R.Keele & L.Valles

Last Update: 4/14/16
 65

Lead: M.Dumas

Last Update: 10/15/15
 66
Consolidate and rewrite entire Professional Development Management ecosystem

Lead: K.Branson
Eliminated

Last Update: 4/13/16
 67
Create VoteUtah.org Website

Lead: M.Dumas

Last Update: 7/8/16
Support Services

 1
Increase number of Professional Development courses offered in local districts

Lead: J.Brooksby

Last Update: 1/5/16
 2
Create train-the-trainer resources for LEA's

Lead: J.Brooksby

Last Update: 4/18/16
 3
Create five new courses

Lead: PD Staff

Last Update: 4/18/16
 4
Create and implement a self paced Canvas course

Lead: M.Hakkarinen

Last Update: 4/18/16
 5
Develop and design UEN Genius Day workshops in order to expand support and training with district specialists

Lead: PD Staff
Deferred

Last Update: 7/14/16
 6
Develop PD-TV by creating just in time weekly content

Lead: J.Covili

Last Update: 4/18/16
 7
Create teacher and administrative features for Digital Teaching and Learning Initiative

Lead: M.Hakkarienen
Eliminated

 8
Deliver TV program highlights to designated Higher Ed. Depts.

Lead: L.Cohne

Last Update: 5/3/16
 9
Increase participation in social media sites

Leads: S.Cohen & R.Finlinson
Ongoing

Last Update: 8/8/16
 10
Expand community partners

Lead: L.Cohne

Last Update: 5/3/16
 11
Broadcast American Graduate Day 2015 on UEN-TV

Lead: K.Anderson

Last Update: 1/8/16
 12
Develop and Expand SciFi Friday

Leads: K.Anderson & J.Gibbs

Last Update: 5/3/16
 13
Support Digital Teaching and Learning Task Force

Lead: R.Timothy

Last Update: 5/3/16
 14
Run Statewide Public Ed. Technology Inventory RFP

Lead: D.Sampson

Last Update: 5/3/16
 15
Run Engineering Study Public Ed. Infrastructure Digital Teaching RFP

Lead: D.Sampson & J.Stewart

Last Update: 1/8/16
 16
Provide telehealth training and assist project sites with clinical implementation

Lead: P.Carroll
5%

Last Update: 9/15/15
 17
Work with state USIM partners to plan the use of telehealth

Lead: P.Carroll
10%

Last Update: 9/15/15
 18
Conduct site visits to telehealth sites

Lead: P.Carroll
10%

Last Update: 9/15/15
 19
Develop telehealth training materials for users

Lead: P.Carroll & D.LaMarche
20%

Last Update: 9/15/15
 20
Facilitate, and present at, the Utah Psychological Association All Day Telehealth Conference

Lead: P.Carroll
5%

Last Update: 9/15/15
 21
Set up telehealth technology to long term care facilities

Lead: P.Carroll & D.LaMarche
0%

Last Update: 9/15/15
 22
Assess and design a solution for distant assessments into the home.

Lead: P.Carroll & M.Cesarini
10%

Last Update: 9/15/15
 23
Support high value programming and outreach choices.

Lead: L.Cohne

Last Update: 5/3/16
 24
Increase the development of PreK-12 and higher ed partnerships that improve educational outcomes across broad student populations

Lead: L.Cohne

Last Update: 5/3/16
 25
Support the development of new broadcast programs

Lead: K. Garrett,
K.Anderson & C.Wood

Last Update: 5/3/16
 26
Produce American Graduate Programming Schedule

Lead: K.Anderson

Last Update: 5/3/16
 27
Expand "SciFi Friday" closed captioning

Lead: K.Garrett & K.Anderson

Last Update: 9/22/15
 28
Investigate and determine FCC Spectrum auction needs

Lead: P.Titus, L.Hunter, R.Timothy & K.Anderson
10%

Last Update: 1/8/16
 29
Increase awareness of UEN-TV programming on 9.1, 9.2, 9.3 to focus on K12, Higher Ed and general public

Lead: L.Cohne

Last Update: 5/3/16
 30
Manage FCC broadcast infrastructure changes due to Spectrum repack

Lead: K.Anderson & P.Titus
Deferred

Last Update: 5/3/16
 31
Create interstitials to support educational initiatives

Lead: L.Cohne

Last Update: 5/3/16
 32
Select vendor to implement new master control operations center

Lead: P.Titus & K.Anderson

Last Update: 1/8/16
Operations

 1
Create UEN branded Graphics Package for UEN-TV

Lead: R.Finlinson & K.Garrett
Last Update: 7/1/15
 2
Support UtahFutures

Lead: L.Hunter

Last Update: 5/3/16
 3
Manage FCC Broadcast Spectrum Repack

Lead: P.Titus
Deferred

Last Update: 5/3/16
 4
Seek and support additional merger opportunities between UEN and UTN.

Lead: L.Hunter & D.LaMarche
Ongoing

Last Update: 5/3/16
 5
Update Board policies and guidelines.

Lead: L.Hunter

Last Update: 5/3/16
 6
Expand consortium licensing based on needs. Document this process.

Lead: L.Hunter
75%

Last Update: 5/3/16
 7
Retrain on and document CPB compliance processes.

Lead: L.Hunter
75%

Last Update: 5/3/16
 8
Build legislative support and advocacy.

Lead: R.Timothy
Ongoing

Last Update: 3/31/16
 9
Support growth and talent development of staff.

Lead: Leadership Group
Last Update: 3/31/16
 10
Identify core and add-on services for UETN constituents.

Lead: L.Hunter
5%

Last Update: 1/8/16
 11
Reprice UTN member fees and services

Lead: C. Chevasuttho & D.LaMarche
10%

Last Update: 9/15/15
 12
Develop UTN Accounting Operations manual

Lead: J.Rees
10%

Last Update: 9/15/15
 13
Complete a communication / marketing plan for telehealth services

Lead: D.LaMarche & R.Finlinson
15%

Last Update: 9/15/15
 14
Build UTN dashboards

Lead: D.LaMarche & K.Krier
0%

Last Update: 9/15/15
 15
Complete catalog of UTN services

Lead: D. LaMarche & J.Gibbs
80%

Last Update: 9/15/15
© Utah Education Network in partnership with the Utah State Board of Education and Higher Ed Utah.
UEN does not endorse and is not responsible for content on external websites linked to from this page.
(800) 866-5852     |     KUEN CPB Compliance    |     Captioning